ADU Guide · Updated November 2026
State rules on size, height, parking and fees, how permits work in Los Angeles, and what an ADU costs, with sources.
An accessory dwelling unit (ADU) is a second, smaller home on your lot with its own kitchen, bathroom and entrance. California gives homeowners strong rights to build one, and those rights expanded again on January 1, 2026.
This guide covers what state law lets you build and how the permit process works in Los Angeles, with cost figures from published 2026 data. It applies across Los Angeles, Orange and Ventura counties, where state law sets the same minimum rights in every city.
California sets minimum rights that every city has to honor. A city can allow more than these numbers, but not less.
| Rule | State minimum |
|---|---|
| Detached ADU size | Up to 1,200 sq ft |
| Size every city must allow | 850 sq ft for a studio or one bedroom, 1,000 sq ft for two or more bedrooms |
| Junior ADU | Up to 500 sq ft of interior living space inside the house |
| Side and rear setbacks | A city cannot require more than 4 ft |
| Height, detached | 16 ft, or 18 ft within a half-mile walk of a major transit stop or high-quality transit corridor, plus 2 ft to match the roof pitch of the house |
| Height, attached | 25 ft, or the height limit for the main house if that is lower |
| Minimum lot size | Cities cannot impose one |
Since 2026, ADU size limits are measured as interior living space, so wall thickness no longer counts against you.
A city can require one parking space per ADU at most. It cannot require any parking for an ADU within a half mile of public transit, in a historic district, or converted from existing space. When an ADU replaces a garage, carport or uncovered parking space, the city cannot make you replace that parking.
Since January 1, 2024, AB 976 permanently bars cities from requiring the owner to live on a property with an ADU. You can rent out the ADU, the main house or both.
The one exception is a junior ADU that shares a bathroom with the main house: then the owner has to live in one of the two. Junior ADUs have to be rented for more than 30 days at a time, and cities can restrict short-term rentals of other ADUs.
Who approves your ADU depends on where the lot sits:
After you submit, the city has 15 business days to tell you whether the application is complete, then 60 days to approve or deny a complete application. If it misses the 60-day deadline, the ADU is deemed approved.
The City of Los Angeles runs a Standard Plan Program with ADU designs that LADBS has already reviewed, which shortens plan check. It also offers a free city-owned plan called YOU-ADU, a 455 sq ft one-bedroom. LA County offers three free pre-approved plans for unincorporated areas: two 1,200 sq ft designs and one 800 sq ft one-bedroom.
Standard plans cover new detached ADUs only, and the city still checks zoning and foundation requirements for your specific lot.
LADBS notes that newly built detached ADUs need solar panels, and that fire sprinklers are not required when the main house does not need them. Hillside lots, coastal zones, historic districts and fire hazard zones add review steps, so check your lot for those first.
Garage conversion on Skyline Drive in Los Angeles, built by SoCal Master Builders. See the project.
Cities cannot charge impact fees on an ADU with 750 square feet of interior living space or less, or on a junior ADU of 500 square feet or less. Larger ADUs can be charged impact fees in proportion to the size of the main house. Units under 500 square feet are also exempt from school impact fees. Plan check and permit fees still apply.
Angi’s 2026 cost data puts most Los Angeles ADUs between $150,000 and $375,000, against a national average of $180,000. Garage conversions land at the low end because the foundation and framing already exist.
What moves the price:
The only reliable number for your lot comes from a site visit. We give every homeowner a clear scope and cost breakdown before any work starts.
Yes. State law allows a junior ADU inside the house together with a detached ADU on a single-family lot. Only one junior ADU is allowed per lot.
No. Since January 1, 2024, AB 976 permanently bars cities from requiring owner occupancy for ADUs. The only exception is a junior ADU that shares a bathroom with the main house.
The city has 15 business days to confirm your application is complete, then 60 days to approve or deny it. If it misses that deadline, the ADU is deemed approved. Pre-approved standard plans shorten plan check.
Not within a half mile of public transit, in a historic district or for a conversion of existing space. Elsewhere a city can require one space at most, and it cannot require replacement parking when an ADU replaces a garage.
Angi’s 2026 cost data puts most Los Angeles ADUs between $150,000 and $375,000. Garage conversions cost less than new detached units because the structure already exists.
Last updated November 16, 2026. This guide summarizes state and local rules for homeowners and is not legal advice. Check your city’s current requirements before you build.
Planning an ADU?
We build detached ADUs, garage conversions, junior ADUs and room additions across Los Angeles, Orange and Ventura counties. Licensed, bonded and insured, CSLB #1119645.